Memo Number |
Title |
Author(s) |
Date |
100 |
Letter To Dr. William E. Howard, NSF |
R. A. Vohden, USNO |
11/06/79 |
101 |
Adding a Remote Antenna To the NRAO Interferometer |
J. Coe |
12/05/79 |
102 |
Interferometer Expansion |
H. Hvatum |
01/08/80 |
103 |
The 34 Acres Property Which Possibly Best Meets the Needs |
R. K. Moore |
01/07/80 |
104 |
Gaudineer Tower |
R. K. Moore |
01/15/80 |
105 |
Letter of Permission: Gaudineer Tower |
D. M. Stack, US Forest Service |
01/14/80 |
106 |
Request To Proceed with Green Bank Interferometer Expansion |
R. A. Vohden, USNO |
01/07/80 |
107 |
Baseline Addition - Interferometer |
R. K. Moore |
01/17/80 |
108 |
Telecon with USNO Klepczynski on 1/24/80 |
F. Crews |
01/24/80 |
109 |
Software Considerations |
B. Meredith |
01/18/80 |
110 |
Additional Baseline To Interferometer: James Vogel Meeting |
R. K. Moore |
02/06/80 |
111 |
Microwave Link Path Investigation |
J. Coe, S. Smith |
02/11/80 |
112 |
Letter of Completion: Gaudineer Tower |
R. K. Moore |
02/13/80 |
113 |
Extension To Interferometer Baseline |
R. K. Moore |
02/14/80 |
114 |
Additional Baseline To Interferometer Tasks |
J. Coe, F. Crews |
02/15/80 |
115 |
Additional Baseline To Interferometer: 02/14 Meeting |
R. K. Moore |
02/14/80 |
116 |
Site for Link Reflector: Hostermann Ridge |
R. K. Moore |
02/19/80 |
117 |
Site for Link Reflector: Asbury Knob |
R. K. Moore |
02/19/80 |
118 |
Extension To Interferometer Baseline |
J. Marymor |
02/19/80 |
119 |
Meeting with Navy Representatives |
R. K. Moore |
02/22/80 |
120 |
Meeting with Navy |
R. K. Moore |
03/07/80 |
121 |
Relocating 85-3 |
- |
03/80 |
122 |
New Telescope |
- |
03/80 |
123 |
Response To Solicitations |
R. K. Moore |
03/28/80 |
124 |
Additional Interferometer Baseline Study |
F. Crews |
04/04/80 |
125 |
RFQ GB-176 |
R. L. Fleming |
08/18/80 |
126 |
Addition To Interferometer Baseline Study |
R. K. Moore |
10/06/80 |
127 |
Budget Estimates and Specifications |
R. Fisher |
10/08/80 |
128 |
Interferometer Baseline Committee Meeting |
R. K. Moore |
10/15/80 |
129 |
Interferometer Baseline |
B. Peery |
11/18/80 |
130 |
Interferometer Baseline: 11/19 Meeting |
R. K. Moore |
11/19/80 |
131 |
NRAO Study of an Additional East-West Baseline To the NRAO Interferometer |
M. S. Roberts |
12/19/80 |
132 |
Possible Surplus Antenna |
B. Peery, J. Ralston, L. Howell, F. Crews |
03/13/81 |
133 |
Approval for the Addition of an East-West Baseline To the Green Bank Interferometer |
R. A. Vohden, USNO |
03/19/81 |
134 |
Power Requirements - New Site - Addition To Interferometer |
B. Peery |
04/06/81 |
135 |
First Construction Coordination Meeting |
R. Fisher |
04/14/81 |
136 |
Authorization To Expend NSF Funds |
S. J. Franko, NSF |
06/11/81 |
137 |
NSF Authorization and Second Planning Meeting |
R. Fisher |
06/18/81 |
138 |
Project Flow Chart |
R. Fisher |
06/23/81 |
139 |
Antenna RFP |
R. K. Moore |
06/23/81 |
140 |
Committee Meeting - June 24 |
R. K. Moore |
06/24/81 |
141 |
Meeting To Discuss Antenna Proposals and Recent Project Developments |
R. Fisher |
07/14/81 |
142 |
Davis-Bacon Rates Re: RFP GB-189 |
R. K. Moore |
07/24/81 |
143 |
Meeting To Discuss Results of Antenna RFP, etc. |
R. K. Moore |
08/10/81 |
144 |
Account and Project Number Use and Control of Materials Purchased |
D. Hovatter |
09/04/81 |
145 |
Antenna Procurement and Project Status |
R. Fisher |
09/03/81 |
146 |
Progress Meeting |
R. Fisher |
09/18/81 |
147 |
Committee Meeting - September 28, 1981 |
R. Fleming |
10/01/81 |
148 |
Various Letters Regarding Price Escalations |
R. A. Vohden, USNO |
09/29/81 |
149 |
Financial Status Report: Interferometer Baseline Addition |
- |
09/30/81 |
150 |
Proposals and Re-Estimate of the Overall Project |
M. S. Roberts |
09/11/81 |
151 |
TIW Subcontract Acceptance |
L. E. Becker, TIW Systems, Inc. |
10/21/81 |
152 |
Progress Report Meeting |
R. Fisher |
11/02/81 |
153 |
Subcontracts AUI-198 and AUI-199 |
J. Marymor |
10/23/81 |
154 |
Minutes of November 9 Meeting |
R. K. Moore |
11/10/81 |
155 |
Subcontracts AU1-198 and API-199 |
R. L. Fleming |
11/06/81 |
156 |
Land Leases for Baseline Extension |
R. K. Moore |
12/03/81 |
157 |
Contract-Administrative Update |
R. L. Fleming |
12/15/81 |
158 |
Progress Review Meeting |
R. Fisher |
01/04/82 |
159 |
Project Schedule and Progress Meeting |
R. Fisher |
01/21/82 |
160 |
Minutes of January 27 Meeting |
R. K. Moore |
01/28/81 |
161 |
Design Review of 14.2 Meter Antenna |
R. Fleming |
02/01/82 |
162 |
New Microwave Links for the NRAO Interferometer |
J. R. Coe |
02/02/82 |
163 |
NRAO Labor Charges To Baseline Addition Project |
D. Hovatter |
02/03/82 |
164 |
Follow-up To 1/26 TIW Presentation |
R. Fleming |
02/08/82 |
165 |
Budget |
R. Fisher |
02/12/82 |
166 |
Commitment Authority |
R. Fisher |
02/23/82 |
167 |
Progress Reports, January and February and Servo Drive Control |
R. Fleming |
03/22/82 |
168 |
Antenna Contract AUI 198 with TIW Systems |
J. Ralston, B. Peery |
04/06/82 |
169 |
Progress Meeting |
R. Fisher |
05/14/82 |
170 |
Monterville Progress Meeting - May 20, 1982 |
R. K. Moore |
05/25/82 |
171 |
NRAO Vehicles Travel To the Monterville Site |
D. H. Hovatter |
06/02/82 |
172 |
Schedule Update |
R. Fisher |
06/14/82 |
173 |
Antenna Contract AUI 198 with TIW Systems |
F. Crews, L. Howell, B. Peery |
06/11/82 |
174 |
14.2 M NRAO Antenna Program: Progress for Month of June 1982 |
J. Adamson, TIW Systems, Inc. |
07/02/82 |
175 |
14.2 Meter Antenna: Revised Schedule Acceptance |
R. Fleming |
07/07/82 |
176 |
Antenna Contract AUI-198 with TIW Systems |
F. Crews, L. Howell, B. Peery |
07/19/82 |
177 |
Progress Meeting |
R. Fisher |
07/22/82 |
178 |
Project Funding |
R. Fisher |
08/10/82 |
179 |
Monterville Progress Meeting - August 4, 1982 |
R. K. Moore |
08/16/82 |
180 |
Delivery Extension |
R. L. Fleming |
09/08/82 |
181 |
Change Order No. 1 |
R. L. Fleming |
09/08/82 |
182 |
Schedule Update and Next Progress Meeting |
R. Fisher |
09/15/82 |
183 |
Monterville Progress Meeting - October 4,. 1982 |
R. L. Fleming |
10/04/82 |
184 |
Events and Correspondence of the Past Few Weeks |
R. L. Fleming |
10/26/82 |
185 |
Point Mountain To Green Bank Microwave Link |
J. Coe |
02/15/83 |
186 |
Progress Report Meeting |
R. Fisher |
02/16/83 |
187 |
Monterville Progress Meeting - February 28, 1983 |
R. K. Moore |
03/02/83 |
188 |
Progress Report Meeting |
R. Fisher |
05/12/83 |
189 |
Monterville Progress Meeting - 5/20/83 |
R. K. Moore, J. R. Fisher |
05/24/83 |
190 |
Progress Meeting |
R. Fisher |
09/07/83 |
191 |
Monterville Progress Meeting - 9/14/83 |
R. Fisher |
09/15/83 |
192 |
Progress Meeting |
R. Fisher |
10/24/83 |
193 |
Monterville Progress Meeting - 11/1/83 |
R. K. Moore |
11/01/83 |
194 |
Progress Meeting |
R. Fisher |
11/28/83 |
195 |
Monterville Progress Meeting - 12/1/83 |
R. Fleming |
12/01/83 |