This page lists GBT miscellaneous unnumbered internal reports, i.e. reports, memos, etc. that were not issued as part of one of the formal, numbered NRAO series.
| Title |
Author(s) |
Date |
| Green Bank Telescope: Project Summary |
- |
02/20/89 |
| National Radio Astronomy Observatory, Green Bank Telescope: Small Subreflector Specification (M2) |
- |
07/18/90 |
| Personnel Assignments to the GBT |
R. D. Hall, G. A. Seielstad, P. A. Vanden Bout |
03/05/91 |
| Pointing Coefficients for Single Subreflector Optics |
S . Srikanth |
03/06/91 |
| First Five Receivers for the GBT |
G. Seielstad |
03/07/91 |
| Green Bank Telescope Groundbreaking Ceremony |
|
05/01/91 |
| GBT Science Working Group Minutes, May 14, 1991 |
|
05/14/91 |
| GBT Science Working Group Minutes, June 11, 1991 |
|
06/11/91 |
| New Spectrometer for the GBT |
A. Dowd |
10/07/91 |
| An FFT Based Power Spectrometer |
Davenport |
10/07/91 |
| Original Proposal Concept |
G. Seielstad |
10/07/91 |
| GBT Science Working Group Minutes, October 15, 1991 |
|
10/15/91 |
| Preliminary Design Considerations |
S. Shears |
11/18/91 |
| GBT Science Working Group Minutes, November 19, 1991 |
|
11/19/91 |
| Observer Monitor and Control Requirements |
J. R. Fisher, F. J. Lockman |
02/92 |
| GBT Receiver Plan |
[F. J. Lockman] |
02/13/92 |
| GBT Spectrometer Requirements |
|
05/18/92 |
| Background Information for the SWG Meeting Scheduled for 27 July 1993 |
|
07/19/93 |
| GBT Scientific Working Group Meeting of September 20, 1994 |
J. Lockman, R. Escoffier |
09/94 |
| Dynamic Analysis of the GBT |
D. E. Hogg |
05/05/95 |
| Major Construction: The Green Bank Telescope, GBT Program Plan 1996 |
- |
1996 |
| Green Bank Telescope Monthly Reports, 1998 |
- |
1998 |
| GBT Budget |
B. Porter |
02/98 |
| Green Bank Telescope Monthly Reports, 1999 |
- |
1999 |
| Differential Measurements Of GBT Tipping Structure Retrorefiector Vibrational Motions |
M. A. Goldman |
09/01/99 |
| Confirmation Of S. Srikanth’s Pointing Coefficients For GBT Single Subreflector Optics |
M. A. Goldman |
09/28/99 |
| First Differential (x,y,z) Measurements of the GBT Feed Arm and Future Plans |
D. H. Parker |
11/30/99 |
| First NPH6 hydrostatic level field measurements and future plans |
D. H. Parker |
11/30/99 |
| A Program for Developing the 3 mm Observing Capability of the Green Bank Telescope |
P. R. Jewell, M. M. McKinnon |
12/02/99 |
| Green Bank Telescope Monthly Reports, 2000 |
- |
2000 |
| Beam Forming Array Technical Working Group |
P. Jewell |
11/00 |
| Beam-Forming Array (L-Band Prototype) |
- |
04/01 |
| Local RFI Mitigation Interference Protection Group |
- |
04/01 |
| RFI Excision Research (MRI) |
- |
04/01 |
| Preliminary Design for a GBT 1 cm Receiver |
G. Watts, R. Norrod, P. Jewell, A. Shelton |
01/02 |
| Correlator Sensitivity Degradation Due to Mis-balancing |
F. Schwab |
08/02 |
| Sample of Baseline Stability of the 2-3 GHz GBT Receiver: Project TAST_SB_02119 |
R. Fisher |
12/03/02 |
| Review Panel Report for the GBT Precision Telescope Control System In-Progress |
- |
12/03/02 |